Working days with NETWORKDAYS

1 / 4

Count the working days for each task. 6 May 2026 to 12 May 2026 is 7 days in all, but not all of them are working days.

keyboard Typing formulas is easiest on a computer with a keyboard.

A1
ABCDEFG
1TaskStartEndWorking daysBank holidays
2Supplier quotes6 May 202612 May 20263 Apr 2026
3Training28 Apr 202628 May 20266 Apr 2026
4Snagging4 Jun 202617 Jun 20264 May 2026
5Testing5 May 202629 May 202625 May 2026
6Site survey20 Apr 202620 May 2026
7Handover23 Mar 202610 Apr 2026
8
9
10
11
12
working days
start, end
Type to enter a value or a formula starting with =. F2 edits, F4 adds $ to a reference.
Study notes

How NETWORKDAYS works

  • What does NETWORKDAYS do?

    It counts the working days between two dates: Monday to Friday, leaving out weekends and any holidays you list. Both the start and end dates count if they are working days.

    =NETWORKDAYS(B2,C2,$F$2:$F$5)

  • Why not just subtract?

    =C2-B2 counts every day, weekends included, and leaves out the start day. For a two-week job that's 13 days instead of 10.

  • How do holidays work?

    List the holiday dates in a range and give it as the third part. A holiday that falls on a weekend is only skipped once. Lock the range with $ so it stays put when you copy the formula down.

  • What if the weekend isn't Saturday and Sunday?

    NETWORKDAYS.INTL lets you choose which days are the weekend, for example Friday and Saturday.

  • How do I find a date some working days away?

    =WORKDAY(B2,10,$F$2:$F$5) is the date 10 working days after B2, which is how most delivery and deadline dates are worked out.